FD MET Event  
1 00:00:00 Launch  
  00:00:08 Meco  
  00:00:38 OMS-2 Burn  
  00:00:50 Post-Insertion Timeline  
  00:01:25 Payload Bay Door Opening  
  00:02:55 GIRA Installation/Configuration  
  00:03:35 PGSC (Laptop) Setup  
  00:03:40 NC-1 Burn  
  00:03:55 Photo/TV System Setup  
  00:04:00 Computer Configuration  
  00:06:15 Robotic Arm Powerup  
  00:06:20 ET Photography  
  00:06:30 Robotic Arm Checkout  
  00:06:30 Wing Leading Edge Sensor Activation  
  00:06:50 ET Umbilical Imagery Downlink  
  00:07:10 Window 4 Camera Downlink  
  00:07:15 Arm Powerdown  
  00:07:20 OMS-Pod Survey  
  00:07:20 Medical Conference  
  00:07:40 Pre-Sleep  
  00:08:30 Crew Sleep begins  
2 00:16:30 Crew Wakeup  
  00:18:42 NC-2 Burn  
  00:19:35 Robotic Arm grapples OBSS  
  00:19:35 OMS Heater Reconfiguration  
  00:20:05 Ergometer Setup  
  00:20:35 Science Experiments Activation (MS2)  
  00:20:50 Starboard Survey  
  00:22:45 Meal  
  00:23:45 Nose Cap Survey  
  01:00:00 NLP Activation (Vaccine Experiment)  
  01:00:35 Port Survey  
  01:00:40 Transfer Preparation  
  01:02:50 OBSS Berthing  
  01:03:05 Laser Imagery Downlink  
  01:03:10 EVA Equipment Transfer Preparation  
  01:03:50 Docking Mechanism Init  
  01:03:55 Rendezvous Tool Checkout  
  01:04:00 Centerline Camera Setup  
  01:04:30 Docking Ring Extension  
  01:05:10 Airlock Docking Preparations  
  01:05:58 NC-3 Burn  
  01:06:15 Pre-Sleep  
  01:06:45 Medical Conference  
  01:08:00 Crew Sleep begins  
3 01:16:00 Crew Wakeup  
  01:16:15 Maneuver to -ZLV +YVV Orientation  
  01:16:30 SIMO Dump (Water Dump)  
  01:17:40 Computer Powerup  
  01:17:55 Rendezvous Timeline  
  01:18:44 NH-Burn  
  01:19:20 Transfer Update  
  01:19:32 NC-4 Burn  
  01:21:05 Ti-Burn  
  01:21:45 RPM  
  01:22:20 Approach Procedures  
  01:23:43 DOCKING  
  02:00:00 HARDMATE  
  02:00:05 Leak Checks  
  02:00:30 Computer Powerdown  
  02:00:30 Orbiter Docking System Ingress Configuration  
  02:01:00 Hatch Opening  
  02:01:45 Welcome Ceremony  
  02:01:50 Safety Briefing  
  02:02:30 Robotic Arm OBSS Handoff  
  02:04:00 EVA Equipment Transfer  
  02:05:20 Transfer Briefing  
  02:05:35 Pre-Sleep  
  02:06:00 Medical Conference  
  02:07:00 ISS Crew Sleep  
  02:07:30 Crew Sleep Begins  
4 02:15:30 Crew Wakeup  
  02:15:30 ISS Crew Sleep  
  02:17:40 ISS Arm grapples MPLM  
  02:18:10 MPLM Unberth  
  02:18:35 Water Container Fill (4)  
  02:18:50 Middeck Transfer Procedures  
  02:19:30 MPLM Installation  
  02:20:00 First Stage Bolts driven  
  02:20:15 Second Stage Bolts driven  
  02:20:40 Arm ungrapples MPLM  
  02:21:10 MPLM Vestibule Pressurisation  
  02:22:25 MPLM Vestibule Configuration for Ingress  
  02:23:05 O2 Transfer Config  
  02:23:50 Contingency Water Container Fill  
  02:23:55 MPLM Activation  
  03:01:50 MPLM Vestibule Closeout  
  03:02:05 Middeck Transfer Procedures  
  03:02:10 MPLM Ingress  
  03:03:30 EVA-1 Procedures Review  
  03:04:30 Pre-Sleep  
  03:05:15 Medical Conference  
  03:07:00 ISS Crew Sleep  
  03:07:30 Crew Sleep begins  
  OVERNIGHT ISS, RRM Surveys  
5 03:15:30 Crew Wakeup  
  03:16:45 ISLE Protocol - EVA Preparation  
  03:17:55 MPLM Transfers  
  03:17:50 Water Container Fill  
  03:18:15 MPLM Rack Installation  
  03:18:50 Spacesuit Purge  
  03:19:05 Spacesuit Pre-Breathe  
  03:20:20 ORMATE Prep for EVA and Installation  
  03:20:45 IV Crew Member Preparation for EVA  
  03:21:15 EVA-1 begins (Duration: 6:30) (Garan&Fossum)  
  03:21:15 EVA-1 Operations  
  03:21:40 Robotic Arm EVA Support  
  04:03:45 EVA-1 Ingress&Airlock Repress  
  04:04:00 EVA-1 Post EVA Servicing  
  04:04:00 Transfer Briefing  
  04:05:30 Pre-Sleep  
  04:05:50 Medical Conference  
  04:06:30 ISS Crew Sleep  
  04:07:00 Crew Sleep begins  
  OVERNIGHT ISS external Surveys  
6 04:15:00 Crew Wakeup  
  04:17:00 Middeck Transfer Procedures  
  04:17:20 Contingency Water Container Fill Focused
  04:18:00 MPLM Transfers Inspection
  04:21:45 Crew Meal Placeholder
  04:22:45 MPLM Transfers  
  04:23:15 Middeck Transfer Procedures  
  05:00:40 PAO Event  
  05:00:55 Face In Space - PAO  
  05:01:05 MPLM Transfers  
  05:02:50 Robotic Arm : OBSS to Undock Position  
  05:04:00 Transfer Briefing  
  05:04:30 Pre-Sleep  
  05:04:50 Medical Conference  
  05:05:30 ISS Crew Sleep  
  05:06:00 Crew Sleep begins  
  OVERNIGHT ISS external Surveys  
7 05:14:00 Crew Wakeup  
  05:16:30 Contingency Water Container Fill  
  05:16:40 MPLM Transfers  
  05:19:30 PAO Event  
  05:20:55 Crew Meal  
  05:21:55 PAO Event  
  05:22:15 Crew Off Duty Time  
  06:02:30 Medical Conference  
  06:03:00 Transfer Briefing  
  06:03:30 Pre-Sleep  
  06:04:30 ISS Crew Sleep  
  06:05:00 Crew Sleep begins  
8 06:13:00 Crew Wakeup  
  06:15:10 MPLM Transfers  
  06:15:45 Spacesuit Checkout&Reconfiguration  
  06:17:15 Contingency Water Container Fill  
  06:19:15 PAO Event  
  06:19:30 MPLM Transfers  
  06:20:40 PAO Event  
  06:20:55 Crew Meal  
  06:21:55 Joint Crew News Conference  
  06:22:40 Joint Crew Photo  
  06:23:00 MPLM Transfers  
  06:23:00 Contingency Water Container Fill  
  07:02:00 Transfer Briefing  
  07:02:30 Pre-Sleep  
  07:02:40 Medical Conference  
  07:03:30 ISS Crew Sleep  
  07:04:00 Crew Sleep begins  
9 07:12:00 Crew Wakeup  
  07:13:30 ISS RS: Soyuz Ops (Tentative!)  
  07:14:25 MPLM Transfers  
  07:14:30 Star Tracker Deact. And Door Closure  
  07:14:35 Robotic Arm: OBSS to Sensor Protection Position  
  07:14:55 Contingency Water Container Fill  
  07:16:05 Middeck Transfer Procedures  
  07:16:35 MPLM Vestibule Outfitting  
  07:17:00 ISS RS: S26 Flyabout  
  07:18:55 MPLM Rack Configuration  
  07:18:55 Middeck Transfer Procedures  
  07:19:10 Crew Meal  
  07:20:30 Robotic Arm: Maneuver to MPLM Viewing Position  
  07:20:40 GLACIER Transfer  
  07:21:45 Crew Off Duty Time  
  08:01:00 Transfer Briefing  
  08:01:30 Pre-Sleep  
  08:02:00 Medical Conference  
  08:03:00 ISS Crew Sleep  
  08:03:30 Crew Sleep begins  
10 08:11:30 Crew Wakeup  
  08:13:50 MPLM Egress  
  08:14:05 MPLM Deactivation  
  08:14:25 MPLM Vestibule Configuration  
  08:15:10 Contingency Water Container Fill  
  08:15:30 Middeck Transfer Procedures  
  08:15:55 MPLM Vestibule Depress  
  08:16:35 Oxygen Tranfer Termination and Teardown  
  08:17:20 Meal  
  08:18:35 ISS Robotic Arm MPLM Grapple  
  08:19:50 MPLM Un-Install  
  08:20:55 MPLM Berthing in Payload Bay  
  02:21:20 MPLM Ungrapple  
  08:22:20 Farewell Ceremony  
  08:22:35 Hatch Closure  
  08:23:05 Leak Checks  
  08:23:10 Centerline Camera Installation  
  08:23:40 Robotic Arm: OBSS Maneuver to Undock Position  
  08:23:50 Rendezvous Tool checkout  
  08:23:45 Various Reconfig Tasks (MS1)  
  09:01:00 Medical Conference  
  09:01:15 Pre-Sleep  
  09:02:30 ISS Crew Sleep  
  09:03:00 Crew Sleep begins  
11 09:11:00 Crew Wakeup  
  09:13:00 Computer Powerup  
  09:13:20 ISS/Atlantis Maneuver to Undock Attitude  
  09:13:48 Undocking Timeline  
  09:14:33 Undocking   
  09:14:45 Initial Separation/Flyaround  
  09:15:57 Separation Burn 1  
  09:16:23 Separation Burn 2  
  06:16:30 Computer Powerdown  
  09:17:00 SIMO Dump (Water Dump)  
  09:18:25 Late Inspection begins  
  09:18:00 Starboard wing Survey  
  09:20:10 EVA Equipment Stowage  
  09:20:20 Nose Cap Survey  
  09:21:10 Port Wing Survey  
  09:22:55 OBSS Berthing  
  09:22:55 Laser Imagery Downlink  
  09:23:55 Robotic Arm Deactivation&Powerdown  
  10:00:30 Medical Conference  
  10:00:40 Laser Imagery Downlink  
  10:01:20 Pre-Sleep  
  10:03:00 Crew Sleep begins  
12 10:11:00 Crew Wakeup  
  10:13:08 Separation Burn 3  
  10:13:20 Cabin Stowage  
  10:13:55 Flight Control System Checkout  
  10:15:05 PICOSAT Deployment Operations  
  10:15:45 PICOSAT Deploy  
  10:16:00 Reaction Control System Hotfire  
  10:16:15 PILOT Operations (Landing Simulations)  
  10:18:15 Deorbit Procedures Briefing  
  10:18:45 PAO Event  
  10:19:00 Crew Meal  
  10:20:00 PAO Event  
  10:20:45 Cabin Stowage  
  10:22:00 Communication Checks with Ground Stations  
  10:22:50 Wing Leading Edge Sensor Deactivation  
  10:23:10 PGSC (Laptop) Stowage  
  10:23:15 Ergometer Stowage  
  10:23:30 Communication Checks with Ground Stations  
  10:23:50 KU-Band Antenna Stow  
  11:00:55 Medical Conference  
  11:01:10 Pre-Sleep  
  11:03:00 Crew Sleep begins  
13 11:11:00 Crew Wakeup  
  11:13:20 Medical Conference  
  11:13:35 Computer Powerup  
  11:13:50 IMU Alignment  
  11:13:50 GIRA Stowage  
  11:14:10 PGSC (Laptop) Stowage  
  11:14:36 Deorbit Timeline begins  
  11:16:25 Payload Bay Door Closure  
  11:18:30 Maneuver to D/O Attitude  
  11:18:36 Deorbit Burn (Orbit 217 for landing @KSC)  
  11:18:27 MILA Acquisition  
  11:19:40 Landing at KSC  



Copyright 2010 Fairbanks Broadband LLC

Wednesday, June 8, 2011

ISS and Shuttle Endeavor from Soyuz TM 01






Copyright 2010 Fairbanks Broadband LLC

Tuesday, June 7, 2011

Shuttle Endeavor and ISS rare classic photo

Here it is taken from the departing Soyuz spacecraft 
Copyright 2010 Fairbanks Broadband LLC